Application Procedure

 

It is essential that all surfaces to be treated are properly prepared to obtain a strong bond between the substrate and the product.

 

Technical tips for working with epoxies

 

 

 

 

FOR BRIDGING LARGE GAPS OR HOLES

FOR VERTICAL SURFACE APPLICATIONS

FOR MAXIMUM IMPROVEMENT OF PHYSICAL & CHEMICAL PROPERTIES

 

If a smooth surface is desired, there are two possible ways to accomplish it.

Note: Reduction of the coating thickness is much easier when the coating is applied than after the very hard and abrasive resistant coating is cured

 

CURE TIMES

TEMPERATURE

5°C (41°F)

10°C (50°F)

15°C (59°F)

20°C (68°F)

25°C(77°F)

30°C (86°F)

Movement or use involving no loading or immersion

4 hrs.

3 hrs.

21/4hrs

1 3/4 hrs.

1 hr.

3/4 hr.

Machining and/or light loading

6 hrs.

4 hrs.

3 hrs.

2 hrs.

1 1/2 hrs.

1 hr.

Full electrical, mechanical or thermal loading

4 days

2 days

1 1/2 day

1 day

20 hrs.

16 hrs.

Immersion in chemicals

5 days

4 days

3 days

2 days

1 1/2 days

1 day

Rule of thumb: Every increase of 10° C above room temperature leads to a reduction of pot life and cure time by 50%

 

 

Chemical Resistance